K43 Fiber Project
Located in Vermont
- Capability
- Electric Infrastructure
- Completion 2021
Project Overview
In 2021, in Vermont, we installed 21 miles of new ADSS fiber-optic cable along an energized 115kV transmission line stretching from Williston to New Haven. The installation took place within the energized space, where our highly experienced linemen worked safely and efficiently to install the new cable and connect fiber control services between substations.
Key Highlights
Most of the installation occurred in off-road farmland and was scheduled during Vermont’s notorious winter and spring mud season to minimize the impact on land and town dirt roads. Access was challenging, with crews using all-terrain vehicles (ATVs) or hiking on foot to reach many portions of the line. Our goal was to install the fiber with the least possible impact to property.
Project Overview
In 2021, in Vermont, we installed 21 miles of new ADSS fiber-optic cable along an energized 115kV transmission line stretching from Williston to New Haven. The installation took place within the energized space, where our highly experienced linemen worked safely and efficiently to install the new cable and connect fiber control services between substations.
Key Highlights
Most of the installation occurred in off-road farmland and was scheduled during Vermont’s notorious winter and spring mud season to minimize the impact on land and town dirt roads. Access was challenging, with crews using all-terrain vehicles (ATVs) or hiking on foot to reach many portions of the line. Our goal was to install the fiber with the least possible impact to property.