skip to main content

Chiller Plant

Located in Syracuse, New York

  • Company Riggs Distler
  • Capability
    • Natural Gas Infrastructure
  • Completion 2026

Project Overview

In 2026, we completed the chiller plant for a university in Syracuse, New York that delivers a fully integrated Central Utility Plant (CUP) expansion through a combination of fabrication and large-scale mechanical installation. Our mechanical team’s scope of work spans the entire lifecycle of the CUP project—from Building Information Modeling (BIM) coordination and 3D modeling to procurement, in-house fabrication of over 10,000 linear feet of large-bore piping, and the installation of major equipment including chillers, cooling towers, and supporting systems.

Explore Project Details

Project Scope of Work Included:

BIM & Pre-Construction

  • Full BIM Coordination for Clash Detection and Integration Across Mechanical, Electrical, and Structural Systems
  • 3D Modeling for All Major Piping Runs (16″–30″ Large Bore) and Valve Assemblies

Procurement & Fabrication

  • Procurement of Major Pipe, Valves, and Specialty Components for Chilled Water and Condenser Water Systems
  • In-House Pipe Fabrication of ~10,000 LF of Piping (16″–30″) with Shop Welds, Spool Assembly, and QA/QC Testing

Mechanical Installation

  • Field Installation of Large-Bore Piping, Valves, Strainers, Expansion Joints, and Supports
  • Rigging and Setting of Major Equipment, Including: (4) Chillers & (4) Cooling Towers
  • Miscellaneous Pumps, Heat Exchangers, and Skid-Mounted Systems
  • Installation of Auxiliary Piping and Interconnections to Existing CUP Distribution Networks

Testing & Commissioning

  • Hydrostatic Pressure Testing of All Piping Systems
  • Chemical Cleaning, Flushing, and Passivation of Chilled and Condenser Water Loops
  • Pre-functional Testing of All Equipment Prior to Start-Up
  • Support of Commissioning and Integrated System Testing with the Owner’s Reps and Controls Contractors

Insulation & Finishes

  • Installation of Thermal Insulation Systems for All Piping, Equipment, and Appurtenances to Improve Efficiency and Safety
  • Coordination with Architectural Finishes in CUP Equipment Rooms

Challenges and Results

The upgraded CUP significantly reduces the university’s steam and chilled water consumption, targeting its largest source of greenhouse gas emissions. Beyond campus, the facility also provides critical utility services to two local hospitals and a second university campus, underscoring the importance of efficient, reliable infrastructure in supporting both environmental goals and community needs.

Previous
Syracuse Univ8
Picture2 (1)
Syracuse Chiller Lift3
Chiller Rigging Syracuse (4)
Next
Previous Syracuse Univ8 Picture2 (1) Syracuse Chiller Lift3 Chiller Rigging Syracuse (4) Next
Previous 0 1 2 3 Next

Project Overview

In 2026, we completed the chiller plant for a university in Syracuse, New York that delivers a fully integrated Central Utility Plant (CUP) expansion through a combination of fabrication and large-scale mechanical installation. Our mechanical team’s scope of work spans the entire lifecycle of the CUP project—from Building Information Modeling (BIM) coordination and 3D modeling to procurement, in-house fabrication of over 10,000 linear feet of large-bore piping, and the installation of major equipment including chillers, cooling towers, and supporting systems.

Explore Project Details

Project Scope of Work Included:

BIM & Pre-Construction

  • Full BIM Coordination for Clash Detection and Integration Across Mechanical, Electrical, and Structural Systems
  • 3D Modeling for All Major Piping Runs (16″–30″ Large Bore) and Valve Assemblies

Procurement & Fabrication

  • Procurement of Major Pipe, Valves, and Specialty Components for Chilled Water and Condenser Water Systems
  • In-House Pipe Fabrication of ~10,000 LF of Piping (16″–30″) with Shop Welds, Spool Assembly, and QA/QC Testing

Mechanical Installation

  • Field Installation of Large-Bore Piping, Valves, Strainers, Expansion Joints, and Supports
  • Rigging and Setting of Major Equipment, Including: (4) Chillers & (4) Cooling Towers
  • Miscellaneous Pumps, Heat Exchangers, and Skid-Mounted Systems
  • Installation of Auxiliary Piping and Interconnections to Existing CUP Distribution Networks

Testing & Commissioning

  • Hydrostatic Pressure Testing of All Piping Systems
  • Chemical Cleaning, Flushing, and Passivation of Chilled and Condenser Water Loops
  • Pre-functional Testing of All Equipment Prior to Start-Up
  • Support of Commissioning and Integrated System Testing with the Owner’s Reps and Controls Contractors

Insulation & Finishes

  • Installation of Thermal Insulation Systems for All Piping, Equipment, and Appurtenances to Improve Efficiency and Safety
  • Coordination with Architectural Finishes in CUP Equipment Rooms

Challenges and Results

The upgraded CUP significantly reduces the university’s steam and chilled water consumption, targeting its largest source of greenhouse gas emissions. Beyond campus, the facility also provides critical utility services to two local hospitals and a second university campus, underscoring the importance of efficient, reliable infrastructure in supporting both environmental goals and community needs.

Previous
Syracuse Univ8
Picture2 (1)
Syracuse Chiller Lift3
Chiller Rigging Syracuse (4)
Next
Previous Syracuse Univ8 Picture2 (1) Syracuse Chiller Lift3 Chiller Rigging Syracuse (4) Next
Previous 0 1 2 3 Next