Texas Resiliency Program
Located in Texas
- Company Linetec Services
- Capability
- Electric Infrastructure
- Completion 2025-2027
Project Overview
We are the prime EPC contractor for the Texas Resiliency Program, a three-year initiative focused on hardening the distribution grid, replacing aging infrastructure, and improving storm recovery performance across South and West Texas. We manage engineering through a strategic partner while self-performing materials management and construction. This structure provides our utility customer single source accountability for cost, schedule, and performance.
Key Highlights
Scaled from zero to 60+ fully equipped distribution crews within 18 weeks, while maintaining schedule integrity, safety performance, and production targets.
Launched engineering activities three months ahead of construction, growing from 32 to 55+ full time designers, ensuring a continuous release of ready for construction work packages.
Established regional material warehouses within the first month to stage, kit, and sequence materials in alignment with feeder releases, ensuring no downtime between design completion and field mobilization.
Project Overview
We are the prime EPC contractor for the Texas Resiliency Program, a three-year initiative focused on hardening the distribution grid, replacing aging infrastructure, and improving storm recovery performance across South and West Texas. We manage engineering through a strategic partner while self-performing materials management and construction. This structure provides our utility customer single source accountability for cost, schedule, and performance.
Key Highlights
Scaled from zero to 60+ fully equipped distribution crews within 18 weeks, while maintaining schedule integrity, safety performance, and production targets.
Launched engineering activities three months ahead of construction, growing from 32 to 55+ full time designers, ensuring a continuous release of ready for construction work packages.
Established regional material warehouses within the first month to stage, kit, and sequence materials in alignment with feeder releases, ensuring no downtime between design completion and field mobilization.